Development projects

Planned Projects

  • Approval of general body is needed for retrofitting of our Jame of mosjid and construction of three storied annexed building with Minatare at the north  An amount of Tk. 5 crores may be required. This money has to be  arranged from Porishod and donations.
  • We propose to construct a 15’ X 10 first food shop in the recovered space closed to garbage point for class iii & iv employees. Also to keep the space in  our possession, avoid using for the urinating purposes. It will help us to close if  any unauthorised shops are still being run inside DOHS. Approval of  3,00,000/- is required if approved.
  • Approval in principle may be accorded for construction of swimming pool by the sponsor.
  • Approval is needed by the general body to purchase physiotherapy machines for medical centers (Tk 9,00,000/- (Nine lacs). However, we have  written to AHQ for supplying the machine.
  • Approval for Tk. 5,00,000/- (five lac) may be accorded for renovation of our basketball ground which is now in deplorable condition.

In Process

  • East side of lane # 1 will be carpeted soon (in good progress). We have approached Cantt Board for carpeting all Lanes and being persuaded.
  • Construction of 2 lift cores are in speedy progress. 1 x service cum passengers’ lift is expected to be installed by December’ 19 & 15 men capacity  passengers lift by December/January’ 20.
  • Children swimming pool will be constructed as soon as the Baridhara DOHS Revised Master Plan is approved by MOD.
  • We have 50 close circuit cameras installed. Work order for 40 CC cameras have been issued. More 24 will be installed to bring all the lanes under  CC camera coverage.

Completed Projects

  • 4000 Sq yds area at lane # 1 (west) has been raised and carpeted at the cost of TK- 9,00,000/-.
  • Walk way leading from mosque to lane # 13 along the canal has been tiled  at the cost of Tk 12,00,000/-.
  • 630 foot wall has been raised with angle from Anannya to Baridhara DOHS gate (cost is not known).
  • 1020 X 5=5100 sft walkway from Anannya to Baridhara gate has been tiled at the cost of Tk. 5,50,000/-
  • Road leading from Joarshara gate to south of Eastern Road has been carpeted spending TK- 9,00,000/-. It was damaged due to laying of 3rd feeder  line by DESCO.
  • 4 X Trolleys have been procured by the Cantt Board for our garbage disposal at the cost of TK- 50,00,000/- for this DOHS. Now these are not being     
  • New garbage point has been made proper hard standing by the Cantt Board.
  • Installation of deep tube well at road 8C WASA has installed 5th deep tube well at road # 8C of our DOHS. WASA is waiting to replace 600 foot 4”  pipe by 8” Road cutting permission is in progress by the Cantt Board  which will be commissioned soon. Residents will not face water crisis at least  for next 10 years.